The Federal Government has commenced testing on the 700 megawatts Zungeru Hydroelectric Power Plant.
This is ahead of the evaluation of electricity from the facility to the national grid.
The Minister of Power, Adebayo Adelabu, disclosed this while providing answers to industry questions contained in a document released in Abuja on Sunday by his Special Adviser, Strategic Communication and Media Relations, Bolaji Tunji.
The minister also stated that the $1.3 billion project, located in Niger State, had been connected to the national grids.
Adelabu said the facility had been completed, adding that its concession process had also been completed.
“The payments by the concessionaire have been made and the official handing over of this plant has been done to the concessionaire, which is Mainstream Energy Limited, who are the current operators of Kainji and Jabba hydroelectric power plants.
“The stage we are now in is technical handing over by the Chinese consultants that built the Zungeru hydroelectric power plant to the concessionaire. This is because there is a one-year defect liability, where these contractors need to be on the project site to ensure that whatever problem occurs within one year, they can fix it.
“They are working earnestly with the concessionaire and the Ministry of Power, together with the Bureau for Public Enterprise to ensure that we conclude the technical handover of the plant.
“I can tell you that the testing stage started yesterday, that the power generation at the plant started yesterday, and that it will last about one or two weeks, after which total production will start. And I can tell you with good authority that the Zungeru power plant can evacuate power. Therefore, it is complete disinformation to say it is not connected to the national grid.”